Effort follows scope, and scope follows the phases
An ERP quote is a forecast of effort across phases. If two quotes differ widely, they almost always describe different work. Breaking the project into phases is the only way to see where.
Our business systems approach map runs from discovery to hypercare. The stage durations below are the ranges on that map; your own are set in discovery.
- Discovery and process mapping, 1 to 2 weeks: how orders, stock and money really move today.
- Solution blueprint, 1 to 2 weeks: data model, roles, approvals and integrations on paper.
- Configuration, 2 to 4 weeks: environments and modules built to the blueprint.
- Data migration and cleansing, 2 to 3 weeks: trial loads you can check against a reconciliation sheet.
- Integrations, 2 to 4 weeks: banks, stores, payroll and shipping.
- Testing and training, 2 weeks; go-live, 1 week; then 4 weeks of hypercare.
Why discovery is the phase to get right first
Every later phase builds on what discovery finds. A spreadsheet nobody mentioned in the first meeting becomes a change request in configuration, a gap in migration and a workaround after go-live. Finding it in week one costs an interview; finding it in week ten costs a rebuild.
The effort buyers forget
- Data cleanup. Decisions on duplicates and inactive records take your team's time, not only ours.
- Testing and training time. Key users need about four hours a week during testing.
- The overlap. The old system runs until cutover, and someone has to freeze data entry at an agreed time.
- The first month-end close. It needs support from the people who built the system, which is why hypercare is part of the plan.
How to compare quotes that are scoped differently
Put each quote against the same phase list. Ask which phases are missing, who does the data cleanup, how many trial migrations are included, and what happens in the weeks after go-live. A lower quote that skips discovery or hypercare has moved the effort, not removed it.
Our project configurator gives a timeline range for the kind of project you describe, from the same phases, along with the team and the risks to settle in discovery.